CRA-Park Road LPA Municipal Bridge Replacement Project
This Project involved upgrading 126’ of Park Road by replacement of the existing reinforced concrete arch bridge with a 24’ span by 10’ rise by 52’ length flat-topped three-sided culvert including approach reconstruction. Design services included surveying and engineering for the preparation of roadway construction plans including a project site plan, reconstruction of the John Street intersection, water line relocation, right of way plans, and preparation of the PS&E package.
Project estimated construction cost was $422,364.
Client: Village of Crestline, 2009.